Schedule

 

2014

AGDC and State of Alaska sign Heads of Agreement establishing the framework for the integrated LNG export project.

The Alaska State Legislature authorizes AGDC to invest in the integrated LNG project on the state’s behalf.

2015

AGDC adjusts pipeline work activities and timeline to recognize that an integrated LNG project is the state’s top priority.

AGDC completes in-state gas demand study and begins to plan and develop gas offtakes.

2016

The integrated LNG project continues technical progress. Pre-FEED is complete.

Federal Energy Regulatory Commission Resource Reports completed.

2015 – 2018

Engineering & Permitting.

2019

Final Investment Decision.

2019 – 2025

Construction.

2025

In-Service First Cargo.